A work in progress

The list presented below is pretty much a day by day account of the progress on our site, with the most recent events at the top.  As of this writing, we've been in the house for nearly a year.  At this point, we're pretty much on our own...no more sub-contractors.  I'm almost obsesed about working on the house, but it takes a lot of weekends to tackle a task of this magnitude.  

 

Click on the pictures for a larger view.

 

Monday

September 4, 2006

It's been quite a while since my last post.  It's Labor Day weekend and finally after nearly three years, I finished the railings on the bridge.  It is now complete.

Saturday

July 16, 2005

 

The plan was to be working outside by now, but all I've done is work on the greenhouse.  Finally, the last finished space at Gage Hill is near completion.  Here are a couple of shots.

Monday

March 21, 2005

 

Well...here it is the first day of spring.  I haven't posted anything about the house for quite a while so I thought an update would be appropriate.  I've spent most of the winter working on the interior finishes of the greenhouse.  This is slow going.

Thursday

August 12, 2004

 

 

Having just finished battening down the greenhouse roof, Acid Test!  We get hammered with rain.  There's still lots of sealing work to do around windows and such, but the greenhouse roof is shedding water nicely and the water infiltration is minimal considering.

Wednesday

August 11, 2004

 

The leaning tower of Gage Hill:  This is the staging we used to do the overhead work on the greenhouse.  This primarily involves making up copper clad African mahogany battens which get screwed down over the glass to hold it in place.  It's a lot of work just moving the scaffolding around and unfortunately it's hot!  We expect to finish this work tomorrow.

Tuesday

August 10, 2004

 

Continuing along:  Although our updates on this website are a bit more sporadic these days, work continues at Gage Hill.  Finally, after waiting about a month trying to find the correct combination of weather and schedule, Paul Miller and I are installing the glass and copper work on the greenhouse.

Saturday

June 5, 2004

Update:  It's been a while since my last post and some folks have asked for some new images to see how things are going.  We're still trying to get the site straightened out...two inches of rain washed a lot of our seed down the hill.  Our lawn's coming up patchy, but it seems to be filling in.  Here are some recent photos.

Saturday

January 3

Epilog:  Substantial completion.

It's kind of tough knowing exactly when to throw the flag on the play, but I guess we're done.  Not really finished...but done, enough.  Architecturally, it's a point known as "substantial completion"...available for the owner's use.    More...

Sunday

December 14

More finishing touches.  Here's the basement stair railing painted and laced with cable.  I believe my cable stretching days are over...at least for now.

Saturday

December 13

Completely WIRED!  After working weekends and nights for several weeks, 3500 linear feet of stainless steel cable is in place...tight like a guitar string.  Tedious work, but we're really pleased with the outcome.

Wednesday

December 10

Goodies and diamonds in the rough!  Finishing touches are starting to show up all over the house.  Today, Dave Mullen, who's provided all of the steel for our project, delivered the guardrail / handrail for the basement stair.

Tuesday

December 2

Our first appreciable snow at Gage Hill.  This shot shows the entry bridge (early in the morning) with the railings completed on both sides.  Inside, we're pretty comfortable at this point...lots of little stuff to finish.

Sunday

November 23

I give up counting days

Signs of life!  It's been several weeks without a web entry.  I've been really busy.  Here are a few shots to bring things up to date...and Gracie...we found the remotes.

Friday

October 31

Day 195

There's still lots to do but we're starting to see finishing touches appear all over the house.  Today, we moved some actual furniture onto the first floor.  Here's a look at the kitchen as seen from the living room and a shot of the ceramic tile and glass block in the master bath.

Thursday

October 30

Day 194

After another long absence from my web responsibilities...a belated report.  Over the last couple of weeks we've been trying to wrap electrical and plumbing, ceramic tile in the master bath and flooring.  Here's a shot of the newly installed carpet against the cork border in the dining room.

Sunday

October 12

Day 176

My more sporadic reporting is the result of my having to work (yes...actual work) on various projects at the house.  In particular, I'm responsible for laying the cork floors.  Here's my first attempt...the office floor.

Wednesday

October 7

Day 172

Buzz...click...click..crackel...OK, We're back.  Sorry for the long absence.  We've been busy establishing temporary quarters at Gage Hill as well as working (physically working) toward finished flooring inside.  In the meantime, the greenhouse framing has been started and kitchen cabinetry is being set.

Thurs. & Friday

Sept. 25 & 26

Days 160 & 161

Well...time's up!  Over these two days, the contents of our house on Taylor Woods were boxed-up and moved to the basement of the new house.  Karin and I are temporarily holed up in a local cabin.  It was a nice try, but sometimes you just can't make things happen.

Wednesday

September 24

Day 159

Please excuse my absence yesterday...we're preparing to move things out of the house at Taylor Woods.  It's a monumental task after eighteen years.  At Gage Hill, sheetrock continued inside and trim continued outside.  The basement stairs were also installed.

Tuesday

September 23

Day 157

Sheetrock and roll around the kitchen!  The sheetrock's now hung, the curves came last.  Now, there's taping to contend with.  Ouside, it rained cats and dogs but Mike Dalaba's crew worked under the eaves putting up the tongue and groove soffit.

Monday

September 22

Day 156

Four days shy of our (not optional) move date and we've established that we're basically screwed.  Despite our best efforts, it's pretty obvious that the house will not be livable by the end of the week.

Friday

September 19

Day 153

More sheetrock, more exterior trim, more stress, less time.  One week to moving day and we're still hanging (as opposed to taping) sheetrock.  Here's the dining room.

Thursday

September 18

Day 152

Once again, my apologies...no picture.  Coming down to the wire (time-wise) we're in a panic trying to get the interior at Gage Hill livable.  The sheetrockers are two thirds done hanging with taping yet to come.  I'm screwing down flooring underlayment and trim continues outside.

Wednesday

September 17

Day 151

Sorry, no picture again.  Today, sheetrock continued inside and exterior trim made progress outside.  I also started installing underlayment in the office in preparation for the cork flooring.

Tuesday

September 16

Day 150

Sheetrock continues.  Here's a shot of the kitchen ceiling almost enclosed.  Outside, siding and trim continue.

Monday

September 15

Day 149

Sorry...no picture today.  I kind of forgot.  On the bright side, the sheetrockers got started today while exterior trim continued outside.  On the downside, we're definitely behind schedule.  We've begun discussing contingencies for living (on a really reduced scale) in the basement.

Friday

September 12

Day 146

Today, siding and exterior trim continued and Rick McGuire returned to the site to do some final grading.  Things are looking good, but there's still lots to do inside.  The sheetrocker's late!

Thursday

September 11

Day 145

With two weeks and a day to go:  Electrical rough-in was completed and inspected today and the house is stocked with sheetrock.  The sheetrocker didn't actually appear on-site today but I hope to see him there tomorrow.  The first siding went up outside.

Wednesday

September 10

Day 144

Work continued inside today getting ready for sheetrock tomorrow.  In the meantime, we got the first look at some exterior trim...corner boards, window wraps, and such.  Siding won't be far behind.

Tuesday

September 9

Day 143

While electricians worked to finish up inside and we get ready for sheetrock, Mike Dalaba and his group moved outdoors.  This is the beginnings of the vented frieze.  This trim runs around most of the perimeter of the house and will provide attic ventilation.

Monday

September 8

Day 142

Onward toward sheetrock.  After what seems like forever, finally the curved kitchen kneewalls were built today.  For the first time, there's some separation between the dining room, the kitchen and the living room.  It feels good.

Friday

September 5

Day 139

Now for some artsy stuff.  In preparation for drywall, Mike Dalaba's crew and construction manager Paul Miller got the first of the curved soffits in the kitchen framed.  These curves (there are more than one) are reflected in the cabinetry layout below.

Thursday

September 4

Day 138

The countdown continues.  Today, the interior furring was wrapped up and the electrical rough-in continued.  This shot shows the beginning of the kitchen soffits.  This will eventually be a light valance.

Wednesday

September 3

Day 137

No picture, but that doesn't mean things weren't happening.  Today, interior furring, painting of windows and doors and electrical rough-in all proceeded.  We're headed for drywall!

Tuesday

September 2

Day 136

With the long Labor Day weekend behind us, the cast returns!  Today we did more grading, finished the insulation, installed the front door, continued work on the interior furring and electric rough-in.

Friday

August 29

Day 132

Starring a cast of thousands!  I visited Gage Hill at lunchtime today...2 excavators, 4 carpenters, 6 insulators, 2 electricians, and (believe it or not) 2 or 3 painters, priming windows and doors.  The photo shows the entry bridge progressing.

Thursday

August 28

Day 131

Many things went on today.  Final grading of the driveway is making progress.  Interior furring got started and we got to see the beginning of the entry bridge.

Wednesday

August 27

Day 130

Today, the insulators insulated and the framers framed but the big excitement was sitework.  Rick McGuire brought his machinery back to the site to start final grading and to build the driveway.

Tuesday

August 26

Day 129

After a mysterious two day absence (Bad!), our insulator  returned today (Good!) and began putting up the layer of foam on the inside of our exterior walls.  Outside, decking continued.

Monday

August 25

Day 128

Today, the primary on-site activity was installing decking.  It's now possible to walk from the garage to the front door (handy!) and beyond.

Friday

August 22

Day 125

This one requires some imagination.  This shot shows our kitchen (at least some of it) in the rough, stacked in Walt Sutliff's workshop.  In addition to making our kitchen and other cabinetry, Walt and Diane Sutliff are the former owners of the Gage Hill site.

Thursday

August 21

Day 124

Ok...it's time to cook!  The insulators came in and banged out a good two thirds of the first floor (basement to come later).  A one inch layer of foam gets applied over the inside of the walls and ceilings.

Wednesday

August 20

Day 123

Almost weather-tight!  The screened porch is now ready to receive shingles.  Once they're on, Mike Dalaba's crew can pop in the remaining windows and our new house will stay dry inside.

Tuesday

August 19

Day 122

For a change, we're experiencing a run of good weather.  Today, the screened porch framing continued and we saw the first decking nailed down on the deck.  Also, plumbing rough-in was completed.

Monday

August 18

Day 121

Today, screened porch framing continued.  Additionally, our propane tank was delivered (soon to be buried).

Friday

August 15

Day 118

The screened porch roof, framed from rough sawn white cedar, began going up today.  This will allow us to make the main house water tight (finally!) and sets the stage for the pergolas.

Thursday

August 14

Day 117

Construction on the "big" screened porch continued today.  Mike and his crew put down a treated plywood deck (it gets covered later) and erected the remaining beams in addition to framing the deck from the screened porch to the greenhouse.

Wednesday

August 13

Day 116

Here's a long awaited event!  The beginnings of the "big" screened porch, off the living room.  We've been held up waiting for cedar but we're good to go.  This will allow us to finish the roof.

Tuesday

August 12

Day 115

Well...today was kind of a non-picture sort of day.  Primarily, plumbing and heating rough-in continued.

Monday

August 11

Day 114

Apparently, I did something awful in a former life or something because the weather continues to plague the project at Gage Hill.  Today, we had periodic showers separated by incredible mugginess.  Mike Dalaba's crew continued framing the deck.

Friday

August 8

Day 111

Lots of good stuff got done today!  The decks continue, the basement areaway was topped-out, Rick McGuire did some grading around the house and cedar rafters for the screened porch were delivered.  I also laid out all of the partitions for the kitchen.

Thursday

August 7

Day 110

Here's something new!  Today, Mike Dalaba framed the first portion of the "wrap around" deck.  When's it's done, this house is going to have a lot of deck.

Wednesday

August 6

Day 109

Today was a day of many flavors.  Mike Dalaba and his crew wrapped up many misc. interior framing issues.  We also started roughing in the heating and plumbing.

Tuesday

August 5

Day 108

I guess the roofing shots are getting a little old, but we're almost closed in.  The right end is waiting for some cedar we need to frame the screened porch roof.  More windows and two of the sliding glass doors were also installed today.  Hot and muggy!

Monday

August 4

Day 107

We're still dodging the weather but today we kind of got a break.  Despite the very warm and humid day, thundershowers held off until late afternoon, allowing Mike Dalaba's crew to nearly complete the roofing.

Friday

August 1

Day 104

Some days, you gotta work with what you can.  Mother nature turned on us once again and today it rained in buckets.  Fortunately, our windows were also delivered.

Thursday

July 31

Day 103

Roof...Roof...Roof!  And it's hot again to boot.  Today roofing continued across the office wing to the entry.    We also saw the first plumbing materials delivered to the site.  Rough-in, both plumbing and heating, will start tomorrow.

Wednesday

July 30

Day 102

Today, more roofing!  Mike and his guys put down ice and water shield and shingles on the garage, then got the roof over the office wing ready to go tomorrow.  Construction manager Paul Miller and his sons Michael and Troy went back to work on the basement areaway.

Tuesday

July 29

Day 101

Moving toward a watertight enclosure.  Today, Mike Dalaba's crew continued roofing as well as some interior framing items we need to complete in preparation for roughing in the heating and plumbing.

Monday

July 28

Day 100

With a week of good looking weather forecast, today we saw the first of our roof shingles.

Friday

July 25

Day 97

Sun!  The sun actually smiled down on Gage Hill today for the first time in what seems like forever.  The master bedroom roof was sheathed along with some miscellaneous framing.  Copper drip edge for the roof was laid out and coated with a patina agent.

Thursday

July 24

Day 96

OK...a little better.  Today's weather was on again / off again but we made a little more progress.  This shot shows the first bits of the entry bridge (If you're gonna have a moat, you gotta have a bridge!).

Wednesday

July 23

Day 95

Rain, rain, rain!  My guess is that the day we nail down the last shingle the sun's going to come out.  Today, we got some more sheathing down on the roof, but I'm concerned about the time we're losing due to the weather.

Tuesday

July 22

Day 94

Mother Nature again treated us poorly, bringing a deluge in the morning.  We did make some progress later in the day, sheathing the garage roof.

Monday

July 21

Day 93

Despite a nasty storm in the afternoon (we're talkin' buckets here) today saw the first sheathing go on the roof. 

Friday

July 18

Day 90

Today our crew spent a certain amount of time running back and forth to the tool trailer to stay dry, but progress was made nonetheless.  This shot shows posts and the perimeter beam going up to the screened porch.

Thursday

July 17

Day 89

Better weather, better progress.  Roof framing and the erection of the posts around the perimeter deck continued today.  This shot shows the dining room hip.  The "cutout" will eventually be infilled with cedar pergola.

Wednesday

July 16

Day 88

Today was a rainout...heavy in the morning.  Things were supposed to improve, but there were enough showers during the afternoon to keep everyone running back and forth to the trailer.  Not much progress.

Tuesday

July 15

Day 87

Today's big event was the setting of first of thirty wood posts that will eventually surround the house at Gage Hill.  These posts support the perimeter deck and also the roof above.  Ultimately, the lower portion of each post will be clad with stone.

Monday

July 14

Day 86

OK...the weekend's over, back at it!  Today, Mike Dalaba and his crew finished framing the front wall of the garage and set the garage roof trusses.  CM Paul Miller and his son Michael continued work on the basement areaway.

Friday

July 11

Day 83

Today was a rainout...the first rain day in a while.  I visited the sight and took this photo to make up for yesterday.

Thursday

July 10

Day 82

Apologies to all...after walking around with the camera in my pocket, I forgot to get a picture today.  There was plenty to see.  The rest of the trusses on the main house are now in place.

Wednesday

July 9

Day 81

No odds and ends today!  Mike Dalaba and his crew Matt, Bob and Chad set the first roof truss this morning and had about half of the house trusses set by the end of the day.  This also involved the final setting of two twenty foot steel beams over the kitchen.

Tuesday

July 8

Day 80

Today was an "odds and ends" sort of event.  The septic system was buried, interior wall framing was completed and most significantly the roof trusses were broken into groups and moved into stacks on the top of the wall framing in preparation for setting.

Monday

July 7

Day 79

With the holiday weekend behind us, we're back at it.  So how about some infrastructure?  This shot shows our septic system.  It's just about the only photo-op I expect to get.

Thursday

July 3

Day 75

The moat takes the next step toward it's final shape.  Looking the opposite direction from yesterday's photo, this shot shows the grading better developed.

Wednesday

July 2

Day 74

It requires real imagination to see where this is going!  This shot shows the first cut made for the moat.  Working from the low point to the high, this pass establishes the proper grade for drainage.  Now that it's setup, a bulldozer will be used to contour the surrounding grade to get proper pitch away from the house.

Tuesday

July 1

Day 73

Today was kind of an "odds and ends" day... framing in the basement was wrapped up and the garage slab was prepared for concrete in the morning.  Also, misc. sitework continues.  The shot included here is for reference.  Tomorrow, Rick McGuire's going to grade our moat.

Monday

June 30

Day 72

Today was not quite as exciting as some recent days.  An overnight thunderstorm left the first floor deck wet, so Mike Dalaba and his people moved to stud the perimeter of the basement.  Sitework continues.

Friday

June 27

Day 69

On what's supposed to be the last day of nasty hot weather, some neat things happened.  Sonatube forms were set for all 30 of the piers that will support our deck.  Concrete will be placed soon.  Lots of earthwork is occurring and the site's finally starting to show it's shape a little.

Thursday

June 26

Day 68

The heat wave continued today (tomorrow's supposed to be a little better) while we pursued framing the last of the exterior walls.  Rick McGuire's on-site working on the grading and backfill.  Tomorrow we'll start excavating the 30 pier foundations that support the decks and eaves.

Wednesday

June 25

Day 67

Framing continues, as does the heat!  Temperatures pushed into the nineties...real  nasty working conditions.  Also today, trenches were prepared for bringing in the water line, electrical, telephone and cable services.

Tuesday

June 24

Day 66

Framing's really fun because there's lots to see at the end of the day.  This shot is looking at the intersection of the office and dining wings with the entry door about in the middle of the picture.  It was a brutally hot day...thanks to all for pushing ahead.

Monday

June 23

Day 65

Not a big day visually, but actually lots of work got done.  Laid out on our first floor deck are all of the top and bottom plates, jacks, jack studs and headers for the entire exterior wall package.  Tomorrow should be most exciting, indeed!

Friday

June 20

Day 62

It's always exciting to stand on a deck for the first time.  Today our framing crew installed most of the subfloor, which allowed me to experience the views from our dining room, master bedroom and office.

Thursday

June 19

Day 61

A good day's work.  Today, Mike Dalaba's crew set almost the entire first floor joist system.  There's still a little blocking and misc. items to install but tomorrow should see most of the subflooring go down.

Wednesday

June 18

Day 60

Eureka!  Our first real carpentry.  Actual framing began today at Gage Hill as Mike Dalaba and his crew began the first floor deck.  Also today, the formwork was stripped from the garage foundation in preparation for backfill tomorrow.

Tuesday

June 17

Day 59

Moving along.  This shot shows the garage foundation after the concrete was placed.  Also today, lumber was delivered for the first floor deck, which we'll get started on tomorrow if the weather cooperates.

Monday

June 16

Day 58

A picture perfect day, but no picture.  Today was beautiful, sunny and in the high seventies.  Mike Dalaba's crew spent the day erecting formwork for the garage foundation which will be poured tomorrow morning.

Saturday

June 14

Day 56

No work was done today, but after two rainouts we stopped by and took a couple of pictures just for fun.  Here's the basement slab, a bit damp (rain) but otherwise quite nice.

Friday

June 13

Day 55

Appropriately, Friday the thirteenth turned out to be a rain day.  At least that way, we shouldn't run into any bad luck.

Thursday

June 12

Day 54

Sorry, no picture today, but things moved along.  The basement slab's now in place and the garage footings were also poured.  Work also continued on our well, which shows improvement but is still turning up flow rates that I wish were a little higher.

Wednesday

June 11

Day 53

What a difference a day makes!  I was actually out of town all day on Wednesday...this shot was taken early Thursday morning.  We're largely backfilled, the steel's all set, the basement slab and garage footings are all set for a Thursday morning pour.

Tuesday

June 10

Day 52

Workin' away!  We discovered substantial water in the foundation this morning which prompted us to reinstall the exterior foundation drain.  Also today, the sub-base for the basement slab was compacted and the garage frost walls were excavated.

Monday

June 9

Day 51

Not much to look at, but important none the less, today was spent installing drains around the foundation and under the basement floor slab.  Tomorrow, we'll place the basement steel in preparation for the slab.

Friday

June 6

Day 48

Here's the foundation all stripped.  Today, we're going to erect some additional silt fencing around the site, put waterproofing on the foundation and prepare some steel beams to be set on Monday.

Thursday

June 5

Day 47

Another non-picture day.  More stripping and preparing the foundation walls for waterproofing.

Wednesday

June 4

Day 46

A non-picture day.  On site activities included stripping the forms from the foundation and the electrical / telephone / cable trench was backfilled.

Tuesday

June 3

Day 45

Probably our most productive day to date, if not the messiest!  The basement walls are poured, plus we laid the primary electric service, telephone and cable and started our well to boot.  The well was down 240' at the end of the day.